As data centers proliferate, utility grid operators face a critical modeling gap: large computational loads can shed hundreds of megawatts in seconds, but outage scheduling systems were built around stable, predictable industrial loads. NERC has issued its highest-tier alert about this risk and is drafting a new 'Computational Load Entity' registration category. With ERCOT's summer transmission outage restriction window already open through September 15, and NYISO's reserve margins razor-thin, the real test this summer isn't just generation capacity — it's whether operators have accurate, up-to-date load models that reflect the data centers that have come online in the past 18 months. Adequate capacity and adequate situational awareness are not the same thing.